PINOS ALTOS
Agnico-Eagle
Dates: 2006 - 2009
Location: Chihuahua, Mexico
6,000 TPD - Heap Leach & Merrill-Crowe
KCA completed a feasibility study for this mill/heap leach project and was subsequently awarded an EPCM contract for this US$134 million mine. Site construction began in early 2008 and startup in 2009. Pinos Altos includes both a 2,000 tonne per day heap leach pad and a 4,000 tonne per day Milling operation which includes an agitated leach circuit, a Merrill-Crowe extraction plant, and a CCD circuit with dry stack tailings.

Grinding Plant


Lime Feed System

Grinding Plant